BC okays Brucejack production increase

North of 60 Mining News – January 1, 2019

 

Last updated 9/25/2020 at 10:32am

High grade gold mine Valley of the Kings deposit northwestern BC

Pretium Resources Inc.

Pretium Resources has the permits needed to increase mill throughput at its Brucejack Mine in British Columbia's Golden Triangle by 40 percent.

Pretium Resources Inc. Dec. 14 said it has received the provincial permits needed to increase the amount of ore fed into the mill at its Brucejack gold mine in northern British Columbia by roughly 40 percent.

The amended permits issued by two B.C. regulatory agencies – Ministry of Energy, Mines and Petroleum Resources; and Ministry of Environment and Climate Change Strategy – allows Pretium to increase the Brucejack Mine production rate to 1.387 million metric tons per year, or 3,800 metric tons per day. This is compared to the previously allowed rate of 990,000 metric tons per year, or 2,700 metric tons per day.

Pretium estimates it will cost less than C$25 million to complete the minor mill upgrades needed to support the increased production. The company plans to minimize downtime by implementing these improvements during regularly scheduled maintenance shutdowns of the mill.

Under the previously allowed throughput rate, the mill at Brucejack has been churning out roughly 1,000 ounces of gold per day.

Pretium ramping up production at the newly built Brucejack Mine in mid-2017, and the operation produced 152,484 oz of gold during the first six months of operation.

Through the first nine months of 2018, the mine produced 279,670 oz of gold from 738,555 metric tons of ore averaging 12 grams of gold per metric ton.

The mill throughput through the first nine months of this year averaged 2,705 metric tons per day.

Pretium anticipates ending the year strong, producing between 117,000 and 137,000 oz of gold during the final quarter. This would boost Brucejack's 2018 production to 387,000 to 407,000 oz.

The permits to ramp up production bodes well for this northwestern British Columbia mine to produce even more gold in 2019.

Pretium will also get to keep more of the gold and silver it produces.

High grade gold mine Valley of the Kings deposit northwestern BC

Pretium Resources Inc.

Pretium anticipates strong final quarter of 2018 production at Brucejack, pouring between 117,000 and 137,000 oz of gold during the last three months of the year.

On Dec. 18, the company announced the closing of a US$480 million loan to refinance its existing construction credit facility. In conjunction with the closing of the loan, Pretium paid US$237 million to repurchase an 8 percent gold and silver stream sold as part of the financing package for the development of the Brucejack Mine.

"With the refinancing of our construction credit facility and the repurchase of the precious metals stream, we have accomplished all of the objectives we set for ourselves at the start of this year, including the achievement of steady state gold production and the receipt of permit amendments to increase production to 3,800 tonnes (metric tons) per day," said Pretium Resources President and CEO Joseph Ovsenek.

The company said a specific timeline for ramp-up to the 3,800 metric tons per day production rate along with an updated mine plan is expected in the first quarter of next year.

–SHANE LASLEY

 

Reader Comments(0)

 
 

Our Family of Publications Includes:

Mining News
Metal Tech News

Powered by ROAR Online Publication Software from Lions Light Corporation
© Copyright 2024

Rendered 04/14/2024 10:24