Author photo

By Shane Lasley
Mining News 

Back River pre-mining progress continues

Crews work above, underground at Goose gold mine project North of 60 Mining News – August 27, 2021

 

Last updated 9/2/2021 at 3:56pm

Sabina Gold & Silver Back River Canada Nunavut Goose Mine resource expansion

Sabina Gold & Silver Corp.

A Cat haul truck and loader delivered to Sabina's Back River gold project in Nunavut on Aug. 23.

Sabina Gold & Silver Corp. Aug. 24 announced that it is making significant progress on large predevelopment projects and the delivery of equipment and supplies that further the proposed Goose Mine on the company's Back River gold project in Nunavut, Canada.

"Tremendous work has been completed during the first nine months of 2021 as we propel the project towards a production decision," said Sabina Gold & Silver President and CEO Bruce McLeod. "We have been advancing the underground exploration ramp at Umwelt, have completed critical civil works at the Goose site, and have prepared the Sabina Port facility to receive the largest sealift planned to date, which is now offloading the first ship. We have also completed detailed engineering and received ... construction drawings for the process plant. In parallel we continue to work towards project financing in order to make a production decision."

A 2015 feasibility study detailed plans for mining four deposits – Goose, Llama, Umwelt, and Umwelt Underground – to feed a 3,000-metric-ton-per-day mill forecast to produce an average of roughly 200,000 oz of gold per year over an 11.8-year mine life.

Since that time, however, Sabina has significantly expanded the resource.

According to a calculation completed earlier this year, Back River hosts 33.45 million metric tons of measured and indicated resources averaging 5.88 grams per metric ton (6.32 million oz) gold; and 13.79 million metric tons of inferred resource averaging 6.44 g/t (2.86 million oz) gold.

Much of the expanded measured and indicated resources are expected to be upgraded to reserves upon completion of an updated feasibility study for the Goose Mine.

In the meantime, Back River crews are continuing to make progress above and underground at Back River.

Sabina's site crew and earthworks contractor have focused on upgrading roads, infrastructure, building laydown pads, and crushing and screening activities. So far, around 10,000 cubic meters of aggregate material for concrete and pond liner underlay has been mined from a nearby site.

The earthworks contractor, a Kitikmeot qualified business, is moving ahead with the rough grading of the plant site area, and pad area for permanent fuel storage tanks which will eventually be used to store fuel for the entire site.

At the same time, another crew is working on an underground decline that will provide a platform for further underground exploration at Umwelt, which hosts much of the resource at Goose. Since the first portal blast at the end of May, crews have completed 130 meters of underground development at Umwelt.

Sabina Gold & Silver Back River Canada Nunavut Goose Mine resource expansion

Sabina Gold & Silver Corp.

Crews have completed 130 meters of underground development since the first blast at the portal of the Umwelt exploration decline on May 31.

Sabina has also completed a workshop and dry storage areas at the site of the underground development. The heated workshop is equipped with a dedicated generator system and mine load centers used to power the underground development, a compressed air system, offices, tool crib, and other facilities.

More than 25,000 tons of equipment and supplies are also being delivered to Back River via barge and ship this summer.

The cargo is comprised of cement, ammonium nitrate, mining equipment, tires, lubes, winter ice road construction and transport equipment, culverts, construction equipment steel and plates, and permanent camp facilities.

To facilitate the sealift, Sabina has prepared laydown storage areas and fuel tank containment at the port site with all sealift activities anticipated to be completed by the end of September.

Author Bio

Shane Lasley, Publisher

Author photo

Over his more than 16 years of covering mining and mineral exploration, Shane has become renowned for his ability to report on the sector in a way that is technically sound enough to inform industry insiders while being easy to understand by a wider audience.

 

Reader Comments(0)

 
 

Our Family of Publications Includes:

Mining News
Metal Tech News

Powered by ROAR Online Publication Software from Lions Light Corporation
© Copyright 2024

Rendered 04/24/2024 19:34